Saturday, February 20, 2010

Dream Garage - Day 64

Since I am out of the retirement mode and back to work, I have not had the opportunity to update the project. So for the past month a lot of the detail work was underway.

  • The electrical, lighting and garage openers are installed. In the lift bay we installed a specially designed garage door opener that allows the door to rise to hug the ceiling so that it will not interfere with a car when it is on the lift. You can see that the opener is mounted on the wall next to the door
  • The exterior has its' stucco put on and is ready for sealer and paint.
  • The interior is done with 3 coats of color.
  • The lift is in storage in Orlando and we are waiting for the epoxy floor to be completed before that will be installed.
  • Exterior paint and final grading is this week, with the final inspection is set for early next week
  • Oh.. and we now have a usable attic!!